An Applied Study to Evaluate the Achievement of School Buildings by Using (CPM)and(Fuzzy CPM) Methods
Main Article Content
Abstract
Abstract
The absence of scientific planning methods in the management of construction project,if neglected,will lead to unsatisfactory performance for all parformance for all parties charged with the completion of the project. This is evident in the lack of comprehensive knowledge of the process of planning,follow-up, and scheduling for the construction of the project from the theoretical and practical aspects, especially when there is vague and unclear data and information or there is a lack of information related to the time period or costs required to implement the project.Therefore,project management must seek to improve that knowledge through the introduction of effective and exceptional scientific methods to ensure a successful and integrated project within the required specifications and in a record period and lower cost. For this reason,it is necessary to find a more practical way to solve this problem through the use of the Critical Path method and Fuzzy Logic theory in order to calculate the optimal time of completion, and this is done through the program(Win QSB)
Article Details
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
References
References
-Badis, Wahiba, Zaidi, Abdel Samad and Qasimi, Fatiha (2010). "Project Management", doctoral thesis, University of Bouira, www.
-Al-Bakry, Sonia Muhammad (1997). “The Use of Quantitative Methods in Management,” Radiation Press, Alexandria. 3- Hawi, Iman Askar (2004) “Using the Critical Path and PERT methods in planning and monitoring the completion of boats / an applied study in Ibn Majid Company.” Journal of the Technical Institute/Basra.
- Hammadi, Abdel Moneim and Mohamed, Bashir (2018). “Using modern technologies to trade off time and cost to complete projects in an ambiguous environment.” Journal of the City of Elm University College, Volume 10, Issue 2, 183-206.
- Al-Jawad, Maha and Kazem, Ali (2020). “Using the Critical Path Method (CPM) in scheduling the project (paving the 1.52 km long street of Al-Amel neighborhood, Side Al-Ayab,” Journal of Economics and Administrative Sciences, Volume 26, Issue 120, 127-145.
- Khalaf, Batoul Attia (2011). “Scheduling Project Management Using Crashing” CPM Networks to Get Project Completed on Time & Under Budget, Journal of Management and Economics/ University of Baghdad, Issue (89).
- Dakhel, Hawraa Hameed (2022). “The trade-off between time and cost in implementing projects using the CPM method / a case study of the project of covering and paving sidewalk streets with services in the center of Basra Governorate.” Higher diploma research / University of Basra
- Abbas, Doaa Bashir (2023). “Using PERT and CPM techniques to analyze the project network, an applied study / Al-Mustafa Complex Construction Project - Al-Hartha District.” Gulf Economist Journal/University of Basra, Volume (39), Issue (57), pp. 1-24.
- Awali, Jihad and Nadia, Tamzin (2017). The impact of organization and control on the success of the project. Study of the renovation project of the Forsan Saeeda Mills branch. Master Thesis.
- Al-Muhyawi, Qasim Nayef and Omar, Zainab (2007). "Using the Critical Path Method (CPM) in planning and scheduling construction project operations (an applied case study)." Revue des Reformes Economiques et Integration into Economie Mondiale, No. 2, 113-135.
-Calp,M.H.,and Akcayol,M.A.(2019)."Optimization of Project Scheduling Activities in Dynamic CPM and PERT Networks using Genetic Algorithms".
-Lewis,J.P.(2010). "Project Planning,Scheduling and Control : A hands-on Guide to Bring Projects in on time and on Budget". Mc Graw Hill Professional.
-Liang,Gin-shuh & Han,Tzeu-Chen(2004). "Fuzzy Critical Path for Project Network".Vol.15,No. 4,pp. 29-40.
-Madhuri,K.& Saradhi,B. & Shankar,N. (2013) "Fuzzy Linear Programming Model for Critical Path Analysis", Int. J. Contemp. Math. Sciences, Vol. 8, 2013, No. 2,pp. 93 – 116.
-Mazlum, M. and Gunerİ, A.(2015). "CPM, PERT and Project Management With Fuzzy Logic Technique and Implementation On A Business". Procedia - Social and Behavioral Sciences 210,pp.348-357.
- Nahmias , Steven .(1997).Production and Operations Analysis, 3rd.ed. Irwin, U S. A. ,P 517
-Sakawa, M. and R. Kubota, (2001). "Two-Objective Fuzzy Job Shop Scheduling through Genetic Algorithm, Electronics and Communications in Japan", Part 3, Vol. 84, No. 4,pp. (60-68).
-Sakawa, M. and T. Mori, (1999). "An efficient genetic algorithm for job-shop scheduling problems with fuzzy processing time and fuzzy due date", Computers & Industrial Engineering, No. 36, pp. (325-341).
-Stevenson, W. J. (2015). Operations Management, 12th ed. McGraw-Hill/ Irwin, New York, New York.
-Zadeh, L. A., ̎(1965)."Fuzzy sets ̎. Information and Control", 8, 338–350.
Revue des Reformes Economiques et Intégration en Economie Mondiale , العدد 2 ,113-135.